538 THE COLLIERY GUARDIAN. March 15, 1918. just on some single props, bore some boles through, put a spindle through, and run it on a level surface. At first there was great difficulty in the placing of the coal on the belt, and a lot fell off before the men adapted them- selves to the conditions, but at the present time they had very little trouble in the absence of angle irons or any side support at all. All the belts they had now— excepting one or two lengths probably which had driving gear under just to give the belt a lead on to the drums—were done with just simply a straight prop fastened with staples on to the props of the face. With regard to the installation at a Durham colliery mentioned by Mr. Jenkins, he would like to ask Mr. Jenkins how many men were working on that belt at the time. Was the Work done in the 2 ft. 8 in. section, or in the 18 in. section ? It would be very interesting to know whether 160 tons were filled off a face 90 yards long, at 18 in. thick. A 90 yard face of a 2 ft. 8 in. seam, cut to a depth of 4 ft. 6 in., yielded about 100 tons. Mr. Jenkins did not say how deep it was cut. If cut 6 ft., it would yield 125 tons. He was at a loss to understand how 160 tons were got off that face, which was only 90 yards in length. On the question of flitting, the speaker said that at the Wbarncliffe Silkstone they had never done it in two and a-balf hours, even when there had been six men to remove the belt. Mr. Jenkins said that a belt conveyor took two men two hours to flit, whilst an electrical shaker took four men each shift to flit. At Wharncliffe Silkstone, it took them above two hours, and required more than two men. Anyone knew very well that if they had a 90 yds. double belt to pull up or to thread between the props, it was an impossibility for two men to do it. He did not know where the information came from, nor anything at all about it, but he knew that that was not his experience at Wharncliffe Silkstone. Dealing with the methods adopted in the North of England, Mr. Jenkins had spoken about a mothergate, and keeping one face in advance of the other by 40 yds. He (the speaker) was afraid that in the seams in which they worked that would not do at all. If they had one gate, and a face on each side of that gate, and they took one face 40 yds. before the other, they were going to have some cutting up in the roof, because they had a cutting on the side of the level, and in the case of Wharncliffe Silkstone they would not be able to maintain the roof. With regard to driving a heading forward, in order that they might run the tubs in and bring the others back, they commenced with that plan, because, after he had been round and got as many particulars as he could, he naturally followed on in the same way that he had seen. For a month or two they continually had the places in the conveyors buried and everything upside down. The results of the adoption of thab plan were still to be seen in the first twenty yards of the district. It not only blew the roof down in the headings, but it also set at liberty the roof down the face on each side, which was worse than coming in. He determined not to do any heading, and since then they had cut across the level; they had it broken in—z.e., the coal taken out— across the level and about two yards on each side; the denting blown up or got up, stowed into the goaf, the flags laid down, and by that meana a corf could be brought and placed at the back end of the one which bad already been pulled to the conveyor. There was room for it. That was the principle they had adopted right through, and they had not done a yard of heading since. If there was a sufficiency of corves, there was no need for the conveyor to stand at all. They did not change the roads. They still kept one full road only, which was the low side road. The empty corf came in and knocked the full one out, twisting it on to the flag next to the face side, and letting it go away. This was simple, and there was no necessity in their case—and he did not think there was neces- sity in any case—to drive headings for the purpose of taking the corves and having them at the back. It was important, in this work, that everything should go like clockwork, because if by any means they were stopped in one face, and had the machine held back, it upset all the arrangements forward, and they had to get in an extra shift or resort to some other expedient. That did happen at times, and was a difficulty for the colliery manager and the under-manager to overcome, but it could be got over if the thing were tackled in a proper manner. It was necessary to have plenty of corves in the level, so that if anything went wrong they could go on, but not at the same rate as was specified in the paper—namely; 160 tons a day. With regard to the shaker conveyor, he believed he started the first in the Barnsley district; but he noticed that that conveyor was now on the pit bank. He had heard of conveyors being taken out at many places, but it did not follow that because they were taken out, unworkable, it was the conveyor’s fault. In his opinion it was, in a great many cases, the fault of the management. If they would only go in for systematic working and systematic timbering, in a proper manner, he had not the slightest doubt that conveyors would come more generally into use than they were at present. They could be used, because they could run in very little room. On the question of removing the belt, Mr. Wroe said that at Wharncliffe Silkstone the belt had only two joints, and, when they had “ run the face off,” they drew out the pin, and pulled the conveyor back into each gate, one into the delivery end and the other into the return end. They then moved up the head—which took, he believed, about an hour and a-half—fastened the rollers on to the props, pulled the belt to, and put the pin in. He should say that it would take four men half a shift to remove one of the belts, which were about 80 yards long. Mr. J. Ensor said his experience of conveyors had extended over the last eight years, and had been very similar to that of Mr. Wroe. Some of the claims put forward about getting an output of 8, 10 or 12 tons per man by the use of conveyors were liable to cause trouble to the colliery manager. His superiors thought that all they had to do was to put in a conveyor of some sort and they would get this output, and things got rather warm if the anticipation was not realised. In his experience, as in that of Mr. Wroe, they could not drive the advanced headings, as their roof was too bad. They also had to set bank bars every two or three feet, which was a detriment to the conveyors; but they had managed to work for eight years, because they had found out the proper way. He was rather disappointed at not finding in the paper any figures as to what really could be done. The seam at the colliery with which he was connected varied from 3 ft. to 3 ft. 6 in., with a bad roof. They had a belt. They had their gates .110 yards centres, and no middle gate at ail. They could not take the conveyor and fill the tub at a lower level than the conveyor, so they ripped down the bank for a certain distance. Their output varied. He was in the position of having a conveyor gate, a con- veyor wall, a machine-cut hand-filled wall, and some hand work, all running practically side by side, and the figures which he would give were reliable. They usually got 230 7-cwt. tubs for a day’s work, filled by 12 men. Those were the men who actually put the coal on the belt. This worked out at about 7 tons per man. But if they counted all the men engaged on the face and engaged on the conveyor, the figure came down to about 4g tons. In the machine-cut, hand-filled section, where the coal was filled into tubs, their usual output was about 4 tons per man, and the hand-cut face gave them about 2J tons. These were figures that the ordinary colliery manager would like to get, just to show what really was done practically, and not a specially-prepared test, where everything was got ready for rushing the thing out. It sometimes happened that a conveyor got buried, and if they took into account the time in which the ground had to be headed out again, the figures of large outputs which they saw advertised were reduced considerably. After his experience, he would not recommend putting in a conveyor where he could get a good pit-tub easily. Mr. Watson Smith said that some time ago he saw an advertisement that 500 tons were filled off 100 yards of face, in a seam 3 ft. thick, in a shift. As he could not get an output like that, he thought it was in the interests of managers that that statement should be investigated, so he wrote to the people who were advertising, asking if they would kindly tell him where this was being done. They replied that they were not at liberty to give the information, but after* some further correspondence they arranged for him to go and inspect one of their installations in South Wales. There he found that the average per man filling on to the conveyors was 4 tons 12 cwt. They were very proud of that figure, but, at the colliery with which he was connected, they got as much in tub stalls, without conveyors. He found that the seam was 3 ft. thick, and he worked out that, in order to fill 500 tons in one shift, off 100 yds. of face, they would have to move the conveyor up four times. He asked the firm to take the advertisement out of the paper, and he thought they had done so; otherwise he should have thrashed the matter out publicly, because statements like that did more harm than good to any contrivances that were put on the market. Managers naturally listened to statements about something that promised to be of use to them, and on the strength of such state- ments they might be tempted to buy appliances, only to find that they got a miserable result compared to what they expected. The President said Mr. Jenkins was not able to be present that day to answer the discussion, but possibly he would be able to do so at a later date. He thought they could take it from the discussion, and from the criticism of the paper that was raised at Leeds, that they should ask Mr. Jenkins to amplify his figures with regard to the tons per man produced by conveyors. There was no doubt that in many cases he had taken the tons produced actually by the collier, and that, as had been pointed out both on that occasion and at Leeds, was misleading. The figures of output should be based on the total number of men employed at the coal face, whether they were colliers, machine men, cleaners up, or men moving the conveyor. He hoped Mr. Jenkins would give them further information on that point with regard to the tables in his paper. The discussion was then further adjourned to the next meeting. Cleavage in Coal.—Prof. P. F. Kendall, of the Uni- versity of Leeds, who is engaged upon important researches into coal, would greatly value information with respect to the vertical cleavage in coal, known to English miners as cleat, slyne or slips. He begs that mining engineers, mining inspectors and mine managers in all foreign and colonial coal fields will kindly direct to him a postcard giving the compass bearing of the principal line of such vertical cleavage in all mines known to them. If there are variations in the direction of cleavage in different parts of the same bed or from one seam to another, a short statement of the variations would be most useful. The name and the locality of the mine and the geological age of the coal deposit should also be mentioned. The Outlook for Pit wood.—If all requirements are to be met during the year 1918 without encroaching upon the necessary tonnage for the conveyance of food, the supply of the Navy and Army, munitions, and other essential commodities, it is estimated that the home production will have to be not less than 2,900,000 tons of sawn wood, and 3,100,000 tons of mining timber, or an aggregate of six million tons, according to the Board of Trade Journal. Before the war the requirements of the mines, aggregating something like 3| million tons of mining timber annually, were satisfied to the extent of probably 90 per cent., or even more, by imported woods. Now the greater part of the pitwood required has to be cut from home woods, and the supply has come forward in a satisfactory manner. In spite of the fact that imports of mining timber fell from no less than 3,451,328 loads in the pre-war year of 1913, to roughly one million loads in the year just ended, the stocks in the hands of merchants and collieries together are now at very much the same level as they were at the end of 1915, the first year-end at which a stock census of mining timber was taken. This year at least three million tons of mining timber will have to be produced in these islands The home production of pitwood last year was a little less than two million tons. So that one and a-half times as much will have to be cut in this country during 1918 if the requirements of the mines are to be met and the output of coal maintained. A “RESPONSIVE” SHAFT SIGNAL DEVICE.* By B. Angwin. In order to obviate the continual cost caused by the need for renewal of the bell wires in the “ knocker line ” system at East Pool, the author started some 18 month ago a search for an efficient, and at the same a cheap, form of answering signal. The device here illustrated and described was the result. Tie term “responsive.” in the sense of meaning simply answering, does not fully denote the capabilities of the appliance. Allowing that the operators are acquainted with the “dot-and-dash” method of sig- nalling, a conversation can readily be carried on between them by means of this instrument. It relies for its operation on the ready transmission of a pulsation of air through a pipe, in conjunction with the fact that a comparatively low pressure of air is required to sound a whistle. It may be mentioned that, whilst carrying out various tests during the course of the experiments, it was found that an air pressure equal to in. of water, or lb. per sq. in., gave a clear note; on the other hand, a pressure of 30 lb. per sq. in., or over, produced simply the sound of escaping air. The drawings show the “shop details” for the cast work required in a working set, and the various parts assembled, with the necessary connections. Slight differences in the details of the shop patterns and the assembled device are due to developments in the design. The present set consists of bored wrought iron pipes for cylinders, wrought iron reducers for cylinder covers, “ Responsive ” Shaft Signal Device. A, Cast iron cylinder and valve box ; B, cast iron air-pump rod; C, cast iron air-pump rod cap (with 5 in. cup leather); D, cast iron lever fulcrum; E, cast iron rod stay; F, cast iron lever; G, gunmetal 4-way branch pipe; H, whistle made of 6in. of 1 in. pipe; H1, silencer made from electric wire tube. two smaller wrought iron reducers and nipples for valve boxes, and levers, fulcrums, plungers, rods and rod stays made on the mine, as was also the brazed four-way junction pipe carrying the whistle attach- ment. These built-up contrivances, six in number, have been in constant use for upwards of 12 months, and are as good now as when first put to work. The details illustrated are for the most part self- explanatory, but it may be well to mention that the 1 in. holes bored in the cylinder near the bottom are to provide inlets for the air at the end of the stroke. A hole is tapped at the bottom end of the pump plunger to facilitate attachment of an extra weight should this be required to bring the pump plunger to its normal position at the bottom of its stroke. It will be noticed that the whistle is shown to be provided with a sliding sleeve silencer. It is not desirable to have a silencer fitted to the whistle in the engine room, as there is a prime necessity for the engine driver to hear the signals transmitted from the shafts, and to be able to reply to them. Silencers may, however, be fitted to all shaft whistles, and the cage or skip onsetter should be instructed to slide the silencer over the whistle hole directly he has finished at one level. This is not absolutely imperative, but it ensures a more distinct sound for other whistles subseqxiently engaged. To comprehend the utility of this “ responsive ” signal in actual working conditions, one may quote some such case as the following :—Let us suppose that the onsetters were at work on the 150 fm. level, and that something requiring immediate attention occurred at the 300 fm. level; a man in the latter level who was conversant with the Morse code could at once send the S.O.S. signal (-----------...--------) consisting of three full, three half and three full strokes of the plunger, together with the distinc- tive number of the level; these signals would be heard both at the 150 fm. level and in the engine room, * Paper presented to the Institution of Mining and Metallurgy on March 7.