1020 THE COLLIERY GUARDIAN. November 15, 1918. as well as nearly ending the proceedings in dire failure. In the ordinary course of sinking, the bottom of the crib is never seen from the time it leaves the surface until it reaches the rock head, as it is con- tinually travelling hi advance of the sinkers. The distance that the crib is in advance is greatest at the commencement of operations, and in the soft mud it reached as much as 4 fathoms in advance. As the sinking proceeds, however, the distance gradually diminishes, and at a depth of 60 ft. the sinkers were able to get down to within 2 or 3 ft. of the bottom of the crib. The Disastrous Attempt.—As a result of the crib coming to a standstill the position became desperate, and as in such condition of affairs warranted a desperate remedy being attempted, and it was this alone that induced the author to sink below the crib in order to make certain that it had freedom to sink. On proceeding, it was found that the crib had passed through the running sand and had entered into tough mud or soft blue clay. The section sunk through so far was composed of— Soil ............................... 1 ft. Yellow clay ... ... ... ... 4 ,, Mud with boulders ... ... ... 50 ,, Sand and gravel ... ... ... 22 ,, Clean sharp sand........... ... 10 ,, —a total of 87 ft. The sand having been cleaned out to the pit bottom, sinking was continued below the bottom of the crib, in order to relieve it. A very few inches of clearance might have been sufficient to demonstrate that the crib and brickwork would sink no further, but some- Fig. 2.—Sectional Elevation of Sinking Crib. thing like 18 in. to 24 in. below the crib had been sunk when disaster occurred. The mud which was being sunk through was tough all over the pit bottom except at one point on the perimeter. Here it was very soft, and latterly burst in, bringing with it the sand and mud above in such quantities that the shaft was more than half filled within the space of a few minutes. Luckily no lives were lost, as precautions had been taken to have four safety ladders hanging down the sides of the shaft, by means of which the sinkers escaped. Not too soon, however, as they expe- rienced the greatest difficulty in claiming as fast as the sand, etc., was rising inside the shaft. As soon as the sinkers were got out, a close inspection revealed the fact that the inrush had extended right from the surface, leaving a hole 3 ft. by 2 ft. at the surface and down behind the back of the brickwork. (Fig. 4.) Plugging the Breach.—The problem now which required solution was how to plug this opening and stop the inrush. Many possible solutions were ad- vanced, and even tried, but without success, and it will suffice to give here a brief description of the last two of these fruitless attempts. (1) Bales of compressed straw were procured and stuffed into the hole at the surface, and these firmly pressed down until the hole was completely filled. Sinking operations were again resumed and the sand filled out until the bottom of the crib had again been reached. It was then found that the straw at the bottom of the crib effectually plugged the hole from where the inrush had taken place. This plan might have succeeded but for unfortunate delays which allowed the straw to rot before full advantage of it could be taken. This decomposition of the straw gave rise to the presence of a pungent odour of gases, probably ammonia or its compounds, in the pit bottom, so strong as to make work impossible. The rotting process continued until the straw gave way and another inrush of sand and mud occurred, again filling more than half the depth of the shaft. (2) The next attempt, after considerable delay, was to try and stop the gap by means of wood piles. These were procured and driven down all round the inside of the crib until every possible escape for the sand seemed barred. Heavy permanent rails bent to the circle of the piles were then fitted inside of them with a view to preventing their collapse. As sinking proceeded a series of rail rings 3 ft. apart were put in, each pile, where necessary, being wedged tight against the ring. The rings themselves were well bracketed and bound together to ensure as much as possible no danger from movement taking place. Not- withstanding all these precautions, and despite the fact that four rings of the rails had been properly fitted in, collapse of the piling took place before the bottom end of them had been reached. On this occa- sion, however, no inrush took place, and even when the displaced piles and rings had been withdrawn the shaft did not fill up any further than the top of the crib. Thus ended the seventh attempt to stop the gap and reach the rock head, during which many months of anxious labour had been spent. The eighth experiment deserves particular atten- tion, because not only was it crowned with success, but it opens up new possibilities of great importance in sinking and in other mining problems, such as dams for holding back water, and stoppings for isolating underground fires by hermetically sealing. Compressed Air and Cementation.—This experiment was nothing else than an adoption of the system now known as the cementation process, and consisted of forcing liquid cement into the sand behind the brick- work. For this purpose two rows of 12 holes each were drilled, one row at 3 ft. and the other at a distance of 6 ft.' above the crib. The brickwork being 2 ft. in thickness, the holes were bored 21 in. long by 2J in. in diameter. A piece of 1^ in. tubing with a screw or flange on its outer end was then inserted in each, and afterwards cemented or grouted in. When the cement holding the tubes in position had set, a in. cock was screwed on to the end of each, and the holes then bored through the walling with a smaller drill, which finished the hole at 1| in. diameter. As soon as the drill pierced the wall the sand blew out with great pressure, but when the drill had been withdrawn and the cock shut, the flow of sand was effectively stopped. After all the other holes had been finished likewise, steps were then taken to fit in the apparatus for forcing liquid cement in through the tubes. This apparatus consisted of two small egg-ended steel boilers, 4 ft. long by 2 ft. diameter, fitted with packing glands at each end, through which passed a longitudinal spindle or shaft. On this shaft were fixed several blades shaped like a propeller, which when turned mixed the cement and water and kept it from setting. (See fig. 5.) The boilers were fitted with a Fig. 3.—Elevation of Rails Built in Brickwork. Fig. 4.—Plan and Sectional Eleva- tion showing Inrush and Subsidence from Surface. i!' 1| in. tube for admitting compressed air- and a 2 in. outlet, to which was attached a 2 in. metallic hose for forcing the cement through the walling. Before commencing cementation proper, it was con- sidered advisable to apply the compressed air freely to each of the holes, in order to make sure that each was clear to take in the cement. In the course of this a discovery was made, which is of great importance. After the compressed air had been applied to about eight or nine holes of the lower ring, an unusual commotion occurred. It began by a heavy escape of air from underneath the crib. The compressed air had found an outlet down behind the brick lining, and escaped out at the bottom edge of the crib in the shaft. On looking down to see what was the cause of the noise, the sand appeared to be creeping up. It was thought that the compressed air had either blown out fresh quantities of sand into the shaft, or that it had got under the sand in the pit bottom and was forcing it up. No time was lost then in turning off the air pressure and preparing for a hurried retreat, when the commotion ceased and all was again still. An examination revealed the fact that the sand was now nearer to the fixed scaffold by 2 ft., but it was now stationary. Air was again applied to the remaining holes of the lower row, all the while watching closely its effect on the sand under- neath, A similar but lesser commotion occurred, which also ceased on the withdrawal of the air pres- sure, and the sand was again noticed to be nearer to the scaffold by another 6 in. Several other applica- tions of air had similar but lesser results until the supposed upward motion of the sand had ceased, and it had now reached a point of about 4 ft. nearer the scaffold than when the air was first applied. A subsequent closer examination disclosed the fact that the foregoing commotions were due not to the sand coming up, but to the sinking of crib and brick work, a most unexpected but none the less welcome occurrence. The whole fabric had moved with the application of the compressed air behind 'the brick- work. It appeared that the air had been sufficient to cause the sand and mud to loose their grip of the brickwork and allow it to slide down as required. In any case it did slide down more than enough to com- pletely close the. hole from which the inrush of sand and mud had so often taken place. It is obvious now that an earlier application of compressed air to both shafts would have expedited the sinking and reduced the cost considerably. Although the need for cementation was now much less, it was decided to carry it out as originally planned, as all the necessary apparatus for that purpose were at hand. - S z £ 2 B Bi W Fig. 5.—Process of Cementation. Fig. 6.—Building of Brickwork in Segments below Crib. The first procedure was to take off the manhole door of the boiler and half fill it with water, into which afterwards was emptied cement enough to make the required consistency. During the whole time the handles attached to the shaft with the stirrers were kept turning in order to thoroughly mix the cement and water and' keep it from setting. The manhole door was then replaced and screwed up tight, and the compressed air at 80 lb. per sq. in. turned on. The outlet cock was then opened and the handles kept turning until the boiler was emptied and the air blew freely through. This procedure was repeated as long as the holes continued to take in cement. One of the holes took in as many as 40 bags of cement, while another took in only 8 bags. This was continued until there was no longer any water in the pit bottom to mix with the cement. The growth of water in the pit bottom up to the start of the cementation process was about 80 gals, per minute, but when cementa- tion had finished the shaft was dry. the cement having effectively dammed the water back and prevented it flowing into the pit bottom. The cementation therefore had not been in vain, and while it was not required to close the hole from which the inrush had taken place, it succeeded in stopping the water, which is always a source of danger when dealing with sand and soft mud. It had the effect, however, of preventing the crib and brick lining