THE COLLIERY GUARDIAN AND JOURNAL OF THE COAL AND IRON TRADES. Vol. CXII. FRIDAY, OCTOBER 6, 1916. No. 2910. Widening of the Upcast Shaft at Tinsley Park Colliery.* By H. J. ATKINSON. The upcast shaft at Tinsley Park Colliery was origi- nally sunk to a depth of 214 yds. to the Barnsley seam about 60 years ago, and was made 9 ft. 6 in. finished diameter. The' lining was brickwork generally 4Jin. thick, but in one or two weak places had been increased to 9 in. In the years 1900-01 the shaft was further deepened to act as the upcast for the Parkgate seam workings at a depth of 462 yds. This lower portion was made 15 ft. finished diameter with the probable intention of the upper portion being widened to a similar diameter at some future time. The centre-line used in sinking the lower and wider portion of the shaft differed by a distance of 1 ft. 9 in. in a north-east direction from the original centre-line, this causing the two portions of the shaft to be eccentric. In 1909 the shaft was further deepened to the Silkstone seam at a depth of 548 yds., to the same centre as the length from the Barnsley to the Parkgate seams, and the diameter was made the same, viz., 15 ft. The object in widening the shaft was, first, to increase the efficiency of the underground ventilation, and, secondly, to instal two cages and to erect a larger pair of winding engines in order to wind the men at this shaft, thereby reserving the downcast for coal turning alone. Surface Preparations. Work was commenced in March 1914, and the whole of the shaft top was enlarged. The new top was built of concrete and brickwork, and was practically constructed around the old shaft top which was afterwards taken down. The old headgear above the shaft top was retained as the temporary headgear during the process of widening, and was fitted with two extra pulleys for the bricking scaffold ropes. Widening Operations. The actual widening was commenced in June 1914, and a general idea of how the bricking and widening operations were carried out will be seen from figs. 1 and 2. During the widening or excavating of the sides the sinkers were protected by a vertical steel shield, the out- side diameter of which was 9 ft. (thus allowing it to pass easily through the brickwork of the 9 ft. 6 in. shaft), and the depth 9 ft. A recess 1 ft. deep by 9 in. wide was formed in the shield to pass the Barnsley haulage rope, and holes were made to hold two 3 by 3 in. channel irons 6 ft. long. The shield was suspended by two ropes passing over the 2 ft. 6 in. pulleys in the headgear to a twin-drum temporary capstan winch. Two 2-ton chain blocks were used between the ropes and the tube shackles, to allow the shield to be moved as required without having to use the capstan on every occasion. In certain places the old brickwork had become dis- torted to such an extent that the shield did not suffi- ciently protect the opening. In these places 3-inch deal boards fitted with a hook were hung from the top of the shield where required, so as to fill up the opening caused by the distortion. The excavating was carried out by the men standing on bhe circular shelf or ledge and filling the debris through the open sides of the cage into the tub. The top of the shield was generally kept about 3 ft. above the level of the excavating, as this was found to afford sufficient safety for the sinkers and also allowed of the dirt being filled into the tub without much difficulty. The dirt falling into the shaft sump was cleaned out at frequent intervals. Stretchers were fixed across the widened shaft at intervals of about 20 yds. to replace the haulage rope boxes taken out of the old shaft. The rope was passed through staples fixed in these stretchers, and served to prevent it swinging about until it could be again boxed in at the new shaft side. Bricking Operations. The bricking scaffold was 14ft. Sin. diameter, and was suspended in the shaft by | inch bull chains from four shackles. An opening was left in the scaffold, in order that the chair should be free to pass through at any time. It being impracticable to use a hoppit or “ bowk,” the debris was filled into a pit corve run on to the chair. Hand-rails were fixed around the opening in the scaffold, and an opening, protected by two movable bars, was left at the front to facilitate the emptying of the bricks, mortar, etc., sent down the shaft. Hand-rails were also stretched across the bull-chains of the cage, and the sinkers were allowed to ride on top of bhe chair. When the necessary depth had been widened and a crib put in ready for a length of bricking, the shield was lowered by means of the chain blocks until the channel irons rested upon the shelf of the excavation. The ropes were detached and drawn up to the bricking scaffold, * From a paper read before the Midland Institute of Mining, Civil and Mechanical Engineers. where they were made fast to the scaffold chains. The chain blocks were taken out of the shaft to be cleaned and overhauled ready for use during the next length of widening. The bolts previously supporting the scaffold were then drawn out of the holes in the brickwork, and ■the scaffold was lowered to the bricking level. The materials, bricks, mortar, etc., were lowered in a pit corve on the chair. When the length of bricking had been completed and the capstan ropes were required for supporting the shield during the widening of the next length, the bolts were knocked out into holes left in the brickwork for that purpose, thus allowing the capstan ropes to be detached and lowered to bhe shield, where they were then made fast, the next length of widening being carried out as previously described. By this system of supporting both the widening shield and the scaffold in the shaft independently of the ropes, it was found possible to carry on the work without having to take them to the surface every time a length of either widening or bricking was completed. A difficulty arose owing to the difference in the centres of the two portions of the shaft. The pulleys for the capstan ropes were fixed along the centre line of the Fig. 1.—Section of Shaft Showing Bricking Scaffold in Use. * le □ 4 Fig. 2.—Section of Shaft Showing Position of Shield during Widening. 15 ft. shaft so that the scaffold would hang freely in the new brickwork. As will be obvious from fig. 2, when the ropes were attached to the shield, it would not hang freely in the smaller shaft, but would tend to swing towards the new centre line. This difficulty was over- come by passing the winch ropes through bhe chair opening in the bricking scaffold, thus causing the shield to hang correctly in the 9 ft. 6 in. brickwork, but necessi- tating it always being raised or lowered by the chain blocks. When paying out more rope the shield was lowered on to the channel irons so that the ropes should not bind on the sides of the scaffold opening. When sufficient rope had been lowered the capstan winch was stopped and the drums fastened, and the blocks were pulled up until they took the weight of the shield again, being lowered out as the “ shelf ” or ledge of the widen- ing proceeded. Dumb Drift. During the widening an interesting relic of old venti- lating practice was found at the Thin coal level at a depth of 80 yds. This was a furnace chimney in the side of the shaft, extending to a distance of 10 yds. above the old landing level, before again entering the shaft. The chimney was at right angles to the old pit bottom; it was circular in shape, and of a diameter of 2ft. 6in., being situated about 3 ft. away from the shaft side, and was lined with a single course of brickwork. Apparently it had been formed to carry the smoke and heat of the ventilating furnace into the shaft at a distance above the inset, so as not to inconvenience the men working at the shaft landing. Temporary Scaffold. Below the Barnsley level bhe shaft gradually “ belled” out to the 15 ft. diameter in a distance of about 30 yds. It was found necessary to take out this ground to the first permanent crib of the old brickwork. A temporary scaffold was required to finish the last 15 or 20 yds. of excavating, as the “ ledge ” afforded insufficient support for the sinkers to work upon. This scaffold was made very similar to the bricking scaffold, but was not fitted with the bolts, etc., and the diameter was only 13ft. Buntings were fixed every 6 ft. for this last portion of widening. The scaffold was then supported on these, and deals were fixed across the buntings as an additional support for the sinkers. Tubbing. At the High Hazel Level about 10 yds. of cast iron tubbing was taken out of the old shaft. No considerable amount of water pressure, however, was found, and it was decided not to insert tubbing in the new shaft, but to increase the thickness of the brickwork to 18 in., and to fill in with concrete between the shaft sides and the brickwork. Cement mortar was used for this length of bricking, and proved quite satisfactory and perfectly water-tight. Securing the Shaft Before Bricking. The securing of the shaft sides before bricking was done by means of backing deals 4 ft. long and 1 in. thick, held in position by wrought iron rings 4 in. deep and J in. thick, there being six segments to each ring, bolted together by four |in. bolts. The rings were supported by wrought iron hanging rods, bent at the top and bottom to hold the rings. The bricking cribs were about 35 yds. apart, all on strong ground, and with the excep- tion of the first (which was made of oak) they were of cast iron, 14 in. wide and 4 in. deep. They were all designed to act as water garlands. Insets. Landing insets were left at each of the three seams passed through, the Kents Thin, High Hazel, and Barns- ley seams. The brickwork was increased to 14 in., and openings were left 6 ft. wide and 8 ft. high. Blasting Operations. The shot holes were put in as shown in fig. 2, and were drilled to a depth of 3 ft. About 13 or 14 were put in at intervals round the shaft, and as near the sides as possible. Two Hardy Patent Pick Company’s com- pressed air drills were used for this purpose, working at an air pressure of 601b. per square inch, and the explo- sives used were of the permitted type. The shots were fired from the surface by means of a magneto shot-firing apparatus, two shots being the maximum number fired at once. The compressed air was taken down the side of the shaft by a range of 2 in. pipes, a Y pipe being fitted at the bottom of the range with flanges to receive the lengths of flexible hose necessary to convey the air to the two drills used. Lighting. The shaft was lighted during the work by two 250 volt 16 candle-power enclosed electric lamps. They were suspended from the surface by two small pulleys fixed in the headgear, armoured cables being taken from small cable drums, over the pulleys and down to the lamps. By these means the lamps could easily be raised or lowered, all that was necessary being to break the “bottle” connection at the sides of the drums, wind the cable in or out as required, and then couple up the cables again by making the connection. This was a neces- sary condition, especially when blasting was to take place. In addition, the sinkers were each supplied with a “ Ceag ” electric safety lamp. Water. Comparatively little water was encountered during the widening, although surface water was found to incon- venience the sinkers to some extent during the first 30 or 40 yds., as, owing to the high velocity of the air in the shaft, the water was blown on to the men with con- siderable force, wetting them through in a very short time. A considerable difficulty was experienced in the upper portion of the shaft during bricking operations, owing to the brick dust being blown into the men’s eyes; but this was overcome by supplying the sinkers with motor goggles. The ventilation was not affected by any appreciable amount during the whole process of the work. Only one accident (and that a slight one) was reported. Rate of Progress. The average rate of sinking was about 10 yds. per week of 11 eight hour shifts. The average total rate of