896 THE COLLIERY GUARDIAN. April 24, 1914. The erection of the engine was proceeded with at once. In the meantime, the main road was widened to 22 ft. for a length of 10 yards on the outbye side of the pit, and a similar width was made between the pit and engine-house. The height over these latter distances is 14 ft. under the girders, which are of steel 1 ft. deep with 6 in. flanges. The distance from the centre of the pit to the back of the engine-house is 78 ft. The shaft landing, 60 yards long, was widened out to 14 ft. by 7 ft. high. The whole of the widened road in the vicinity of the pit top has brick walls 18 in. thick, in order to carry the girders. The widening and completion of the road round the pit was completed by July 1909. At the same time as the engine-house was being made, the rope-drift was being driven uphill out of the engine-house at an angle of Fig. 3.—Cage on Movable Platform in Tunnel- 50 degs., so as to reach the shaft at a suitable height above the landing level. This drift was so shaped that the ropes passed up the pulleys without touching the sides at any point. The shaft was 17 ft. in diameter before being bricked, and was sunk uphill for a distance of 18 ft. above the point where the rope drift entered. This space was made for the pulleys, and to enable the timbers for carrying same to be got into position with ease. The first crib was laid at the point where the rope drift entered the shaft, and brickwork 14 in. thick was put in. The roof over the shaft was made secure by fixing girders of suitable length close together, and old ship plates were used to make a close covering, so that nothing could possibly fall from above. This upper sinking was carried out in the red marl, which gave some trouble, as it began to weather and flaked off. The rope-drift was in strong sandstone, and was left unlined except for an arch 7 ft. wide, which was turned in close to the pit. The whole of the ground in which the engine-house and main road were driven con- sisted of strong sandstone—a circumstance which was of material help. Sinking now commenced downhill in order to make a connection with the main road at the bottom level; at the same time sinking was commenced uphill from the bottom level, so as to meet the top sinking; and a holing was made in August 1909. The total distance from the level of the bottom road to the top of the shaft is 62 ft. The second crib laid was on a level with the girders of the roof of the lower- road—that is, 14 ft. from the floor level—and as this crib was adjacent to the pit-top entrance for the main road, it was necessary to make a strong job. Two steel girders measuring 23 ft. long by 14 in. deep were placed side by side on each side of the shaft, and built into the side walls; a pitchpine frame of timber of 14 in. section, mortised together, was laid on the girders, and the four ends built into the side walls. The oak crib, 14 in. wide by 6 in. deep and 14 ft. in diameter, was laid on this frame, and the brickwork, 14 in. thick, was then built up to the top crib. The work of completing this part of the sinking took until September 1909. The whole of the drifting and stonework in connection with the making of the pit top was done with the aid of hammer drills of the Flottman type, working with an air-pressure of 50 to 60 pounds. As many as eight drills were working at the same time, and they proved quite satisfactory, the speed of the drilling being fairly fast. These drills certainly beat hand labour in point of speed in the sandstone which had to be dealt with ; in fact, without a drill of this type the work would have been impossible, owing to the inaccessibility of many of the places where holes had to be put in. During August 1909 preparations were made for fixing the winding engines, which it was decided should be placed on a timber frame made of baulks 16 in. square. The cross-pieces were cut into the rock, and afterwards solid brick pillars were built under the timbers, in order to support and fix the whole weight of the installation. The engines were taken down the pit during one week-end, conveyed inbye, and stabled in an old road part way to the sinking, from where they were transported as required. They consisted of a pair of 22 in. cylinders, with a 3 ft. stroke and drum 6 ft. in diameter, direct coupled and fixed on girder bedplates. The diameter of the drum was subsequently increased to 7 ft. A powerful brake of the post type was fitted to the engines, and worked by the foot at the time of erec- tion, but subsequently, in 1912, the engines were fitted with a Melling overwinder and a brake cylinder actuated by compressed air, so arranged that in the event of the failure of the compressed air the brakes will come on and hold the engines. This device was a strong feature in respect of safety, when the peculiar position of the winding engine is taken into consideration. While the engines were being fixed on their founda- tions, a drift measuring 10 by 6 feet was driven at right angles up to the engine-room, so as to provide room for the air-receivers, six of which were fixed in that space, and two more at the back of the engines, one on top of the other. The receivers were 10 ft. in length by 3 ft. 3 in. in diameter, and made of steel plates. The work of widening and making height near and at the pit top was by no means easy, as the roof had to be supported during the operation. Until this stage, however, no mishap had occurred; but when the walls were up and the girders were being got in, a very large piece of sandstone rock, 3| ft. thick and 15 ft. long, came away just over one of the walls, causing the death of a loader. This stone had been tested with a pick not an hour before, but, owing to its thickness and close-grained nature, it rang sound and appeared to be secure. This accident illustrates the difficulty experienced in making quite sure that the apparently solid rock is safe. The only reason that could be assigned for the fail of the stone was that it had been shaken by heavy shotfiring recently carried out in this place. During September 1909 the sinking pulley was fixed on strong pitchpine cross-timbers, 14 in. square, built into the wall on one side, and resting on a cross-timber in the mouth of the rope drift on the other side of the pit. At the conclusion of the sinking, these timber baulks were removed, as they showed signs of decay on account of the excessive damp. They were replaced by four steel girders of suitable lengths, 14 in. deep by 6 in. wide, so placed that two pulleys could be mounted for coal-drawing with two cages in the shaft in the future. While fixing the pulley for sinking, a strong detaching plate was fixed 7| ft. below the pulleys, as a detaching hook of the King's type was used during sinking operations. Sinking Operations. During the third week of September 1909 a start was made in the sinking from the low-level road, and the first few yards of rock were soon got out. It had been decided to use a travelling bridge over the sinking, so Fig. 4.—Winding Engine. that some of the bottom stone on the outbye side of the shaft had to be removed, in order to allow the top of the bridge to come down to the existing rail level of the main road, so that the tubs might be easily moved on and off the bridge. While this work was being performed, the erection of the winding engines was completed, and a flattened strand rope 1 in. in diameter and 400 yards long was put on the drum. The rope was of special construction, so as to ensure non-twisting, its breaking load being 48 tons. No guides were used in the shaft, and consequently no rider was required. The “ bowk ” used was so designed as to hold enough stuff to fill the colliery tub in use, the average load being 18 cwt. of dirt. The bow of the bowk was made of 2| in. round iron, and was fitted with two safety catches. The inside bottom of the bowk was boarded over in order to preserve it; the sides were 3 ft. 9 in. in height by J in. in thickness, the diameter of the top being 2J ft. A strong spring hook for attaching the chain to the bow was used. By the third week in October 1909 a depth of over 90 ft. was reached, when the sinking was temporarily stopped for reasons that are unnecessary to detail in this paper. During this short period of sinking everything had been found to work satisfactorily. During the stoppage, a small dynamo of 6.1 kw. and 220 volts was put in and direct coupled to a Bumsted and Chandler engine, with cylinders 5 in. in diameter, for lighting purposes. It was felt that it was absolutely essential to have a good light for sinking and round the pit top. The set was put to work, but the direct-coupled engine was shortly discarded for a belt drive, the reason being that the engine continually froze up, owing to the high speed run—namely, 675 revolutions per minute. This difficulty can be overcome by using a reducing valve, but a larger cylinder is required. A slow-speed engine, running at 120 revolutions per minute, was put in, with a flywheel and governors, and no further trouble ensued. Sinking was not resumed until July 1910, when it was decided to work on the same system of shifts as before, that is, three shifts working from Sunday night at 10 p.m. to Saturday at 10 p.m. Once started, the sinking proceeded rapidly, as the following table will demonstrate, as it shows the amount of sinking and bricking done between July and March 1910:— Yards sunk and bricked. July ................... 21 August ................. 39 September .............. 40 October................. 46 November ............... 39 December................ 34 January ................ 37 February ............... 26 Mai ch ................. 27 Total ................ 309 This gives an average of 34 yards per month. The total depth sunk was 347 yards, and of this 38 yards were sunk prior to July 1910. The sinking was let to a contractor, but was supervised by the management. The securing of the shaft before bricking was by means of backing-deals 4 ft. long by 1 in. thick. These deals were held in position by wrought-iron rings 5 in. deep by f in. thick, bolted together by four bolts at each point. There were six segments to a ring, the rings being suspended by wrought-iron hanging-rods in. in diameter, suitably bent top and bottom so as to catch hold of the rings. The first ring below the last bricking crib was suspended by chains fixed to the crib. The bricking cribs were placed about 35 yards apart, each crib bed being carefully prepared on strong ground. Iron plugs in addition were required in some places. Most of the cribs were 14 in. broad and 6 in. deep, and were all made of oak. At first sight the distance between the bricking cribs may seem excessive, but the writer contends that, owing to the fairly good ground passed through, and also to the careful timbering of the sides, the satisfactory results quite justified the distances apart. Further, the exceptional circumstances of sinking underground, and the difficulties of getting the bricking scaffold in and out of the shaft, made it necessary to go as far as it was reasonably safe before commencing to brick, so as to avoid excessive labour; moreover, once the scaffold was in the shaft, it was advisable to do as much bricking as possible. Sinking and bricking were not carried on simul- taneously. The bricking scaffold was constructed with an under framework of two steel channels 10 in. deep, with 4 in. distance pieces between of similar size. In addition to this centre-piece, two wing-pieces were made to hinge on to each side of this framework, these flap pieces being detachable. The whole scaffold was 13 ft. 9 in. in diameter, and was covered over with boards 3 in. thick. In order to give extra security, eight square iron bolts of 2 in. section were made so as to push over and into the brickwork. The bricking scaffold, with eight men and materials, weighed about 5 tons. It was manipulated by a special crab engine with two drums geared 40 to 1 by worm-gearing and driven by a pair of cylinders 6 in. in diameter. Plough-steel ropes l|in. in diameter were attached to the drum, and passed over small pulleys down the pit, the two pair of bridle chains being attached to the steel frame of the scaffold by strong D-links. The drums of the engine moved together, and consequently no tipping of the scaffold could occur. The type of crab used was eminently satisfactory, being self-contained and capable of easy handling. The ventilation of the sinking had to be carefully considered, and to carry this out a Bumsted and Chandler fan and engine were installed. * The fan was Fig. 5.—Bumsted and Chandler Fan. placed in such a position that a constant supply of fresh air was obtained, which was forced down air pipes. The air pipes were 24 in. in diameter and 6 ft. long, with mouthing ends; but after the sinking was completed flanged air pipes 9 ft. long and of the same diameter were fixed, and were found to be more airtight and stronger. The fan was 5 ft. in diameter and 1 ft. wide, running at 250 revolutions per minute, and at this speed 6,000 cubic feet of air per minute was constantly main- tained. The fan was placed in the intake 300 yards from the pit top, the air being carried down to the pit, and at the top an elbow pipe was fixed so as to get the range of pipes down the pit. These pipes were slung at