788 THE COLLIERY GUARDIAN. April 9, 1914. MANCHESTER GEOLOGICAL AND MINING S CIETY. A meeting of this society was held on Tuesday last at the society’s rooms, 5, John Dalton-street, Manchester. In the absence of the president (Sir Thomas Holland), the chair was occupied by Mr. Charles Pilkington. Mr. John James Reynolds, mining engineer, Parr’s Bank-buildings, Manchester, was elected a member federated, and Mr. Thomas Hopkin Thomas, 30, Gilmour-street, Tonypandy, South Wales, was elected as an associate member federated. Deepening a Shaft by a Rise Method. Mr. Hugh Brocklehurst Pilkington read a paper on this subject as follows :— At the No. 2 pit of the Newtown Colliery, belonging to the Clifton and Kersley Coal Company Limited, two mines only used to be worked—viz., the Trencherbone and Cannel—and many years ago a level tunnel was driven in each direction, seating the Trencherbone mine to the south and the Cannel mine to the north. As the Trencherbone mine was getting exhausted, and also the rise coal in the Cannel mine, it was decided to deepen the shaft and drive another tunnel immediately under the first one, but 65 yards lower, seating the lower part of the Cannel mine to the south of the pit and the Plodder mine to the north. As, however, the Mo. 2 shaft was at that time very busy winding coal, it was decided to open out in narrow work in the Lower Cannel mine, and drive the tunnel above mentioned from the Cannel to the Plodder in such a position that when the shaft was deepened it would intersect this tunnel. When the time came for deepening the shaft, a con- siderable difficulty arose, as there were only a few hours in the night available for sinking—the shaft being an extremely busy one—as the following will show:—Coal- winding started at 6 a.m., and continued throughout the day until 5.30 p.m.; at 6 p.m. a nightshift was let down, and also between that time and 10.30 p.m. waterwinding had to be resorted to, when 200 tons of water were usually dealt with; at four o’clock next morning the firemen had to be let down ; and further, between 10.30 p.m. and 4 a.m. portions of the night shift were constantly coming to the bottom of the shaft wanting to be wound out. It will therefore be seen that there was practically no time for sinking in the ordinary manner, for even had it been possible to protect the sinkers from coal falling down the shaft, the debris from the sinking could not be wound out when any other work was being done. With these difficulties confronting them, the management had to consider the advisability of deepening the shaft by a rise method. They obtained what information they could from mining papers as to how this had been accomplished before, but they could find no way which to their minds was satisfactory or safe, the methods, so far as they could learn, up to then being very crude, the particular danger being that men were always liable to injury from falls of debris while being wound up the shaft, unless there was some permanent covering. The difficulty was to design a covering which should be easy of access, convenient, and safe to work both under and above, and yet be able to withstand the shock of shotfiring and accompanying falls of debris. After a good deal of thought, however, Mr. Percy Wood invented the scaffold which the writer is about to describe, and which he thinks overcomes the difficulty and danger hitherto existing with this class of shaft driving. Mr. Wood wishes to state that much of the success of this scaffold was due to Mr. James Files, who acted as draftsman, and arranged many of the details. It was decided to commence operations in the shaft from the Cannel Mine, which was 40 yards below the bottom of the existing No. 2 shaft and 12 yards above the lower tunnel. This had the advantage of leaving both the pit bottom and the tunnel untouched; the pit, therefore, was free to wind coal, and the traffic through the lower tunnel to be sent forward without any interruption. Another important feature, which helped in no small degree to the success of the scheme, was the putting down of a 10-in. borehole from the bottom of the existing shaft to the road driven in the Cannel mine from which the shaft was to be started. This borehole served three purposes : it enabled a plumb line to be put through, so that the new shaft should coincide perfectly with the old shaft; it formed an excellent means of ventilation for the rising shaft, and by lowering the capstan rope from the surface through this borehole it enabled the sinking scaffold to be moved as and when required. Had it not been possible to get the capstan rope to the scaffold, it would have been necessary to have raised it from time to time with hydraulic jacks, which would have considerably delayed the sinking. Except when blasting or winding water, the capstan rope was always kept in this borehole ready to be attached to the scaffold each time it was required. As this borehole did not make a great amount of debris, it was found possible to keep it going while the pit was working by putting a strong protection across the bottom of the shaft to protect the workmen, the debris being piled round the bottom of the shaft and wound out in the short time that was available at night. So as to enable water to be wound while the sinking was being carried on below, a pipe was placed in the top of the borehole, sticking up some distance above the bottom of the shaft. This pipe was secured by clay and concrete to keep the water back, thus making a water- tight sump for the tanks to dip into while keeping the borehole quite dry. The first operation when the bore- hole reached the road in the Cannel mine was to blast a quantity of roof down so as to enable the sinking scaffold to be erected in position under the borehole. The scaffold itself is a double-decked one, the upper deck being the working floor for drilling the roof and trimming the sides, the lower deck being used as a banking level and bricking scaffold. The top deck was built 16 ft. 9 in. in diameter, the finished diameter of the pit being 16 ft., and always rested on the brickwork during drilling and blasting operations. It was con- structed with a square opening 5 ft. in size on one side of the centre line. The framework consisted of three parallel baulks of pitch pine, 12 in. by 9 in., planked over with 3 in. planks covered with old boiler plates. The lower deck was 6 ft. 3 in. below the top deck, and was secured by four main posts at the corners of the opening previously referred to, and also by eight 2 in. iron bolts round the edge of the framing. This deck was built 15 ft. 8 in. in diameter, being 4 in. less than the inside diameter of the finished pit—viz., 16 ft. Two openings were provided here 5 ft. square, one being directly below the opening in the top deck, and the other symmetrically opposed to it on the other side of the centre line, and through this this hoppet was raised, and the men and materials landed on to the lower deck by means of two small pulleys fixed above it to take the winding rope used for the hoppet. This opening was protected by three movable bars. The other opening, which had the four posts at each corner, was planked in from the lower to the upper deck, thus forming a box. Two small rectangular manholes were cut in two sides of this box, and these formed the means of reaching the top scaffold. The floor of this box was formed by two doors, which opened downwards, and as the safety of the workers, both on the scaffold and at the bottom of the shaft, depended on these doors, special precautions were taken to keep them shut. In the first place, they were heavily counterweighted until they could support more than the weight of a man, even if not secured in any other way; secondly, they were fitted with a powerful screw brake, which was always kept screwed hard on; and thirdly, there were two trigger catches, which were operated by a hand lever, and which advanced under the doors when they were shut. The doors themselves were of solid construction and armoured with iron plates. These precautions were necessary to prevent any debris falling on to the men when ascending after blasting, or when working below the scaffold filling out the debris. There were also two small emergency doors to get from the bottom deck to the top, in case the main way was impeded by any large stones. The lower deck was also fitted with six ordinary prids of substantial design, and which were used in the ordinary method. Four diagonal stays were fitted from the framing of the lower deck—and these were also bolted to the top deck as they passed through—to take the weight of the scaffold when attached to the bridle chains, which were attached to the capstan each time the scaffold had to be raised for putting in a new length of brickwork; after this was finished the scaffold was packed up and the main baulks allowed to rest on top of the brickwork, and the prids on the lower deck knocked into holes left for them. When the scaffold was thus doubly secured in this position, the capstan rope was detached, and the chains let slack on to the top deck so as to leave a free and open space for work, and to remove the capstan rope away from any danger from blasting. At a later date a strong iron girder and two under tie bolts were added underneath the lower framing. As the engine required for this work had only to raise and lower the men and bricking materials to and from the scaffold, a 7 in. coupled engine with drum was quite sufficient, and this was placed in the Cannel level some 35 yards away from the pit, the rope passing under a pulley at the mouthing and so up the side of the shaft and over the two small pulleys previously mentioned, and then down to the hoppet. An electric signal bell was connected from the scaffold to the engine. To facilitate filling the loose debris into tubs, plates were laid on the floor, level with the Cannel mine. The tubs when full were removed by the main downbrow engine at convenient times, and sent into the workings. As a good light on the roof was a sine qua non, portable electric lamps were used, each box of batteries having two 8-candle power lamps on flexible hose 1 yard in length. These could be put in any position, and gave a good light in all directions. Two boxes (four lights) were used at a time, and there is no doubt these contributed in a very large measure to the safety of the men. The procedure during a complete cycle was as follows: The top deck of the scaffold would be resting on the completed brickwork, and the prids on the lower deck would be in holes some 6 ft. below the top of the brick- work. The sinkers, on arriving at the bottom of the shaft at the Cannel mine, entered the hoppet and ascended to the scaffold. Then they examined the gear, saw that the doors were locked and the brake was on. All being correct, the foreman—after making sure that the roof immediately above the box was sound-r-would then enter the box. As a matter of fact, the roof nearly always came to a good bed over the centre of the scaffold. He would then sound the rest of the place with a long pole kept for that purpose, and also used for knocking off any overhanging flags. The sinkers, to protect themselves, used to set props off the top deck of the scaffold to the roof before drilling. They then put in their shot-holes, and these, through being for the most part almost vertical, went in with surprising rapidity, as the drills always cleared them- selves whether hollow or spiral ones were used. The holes were then charged, and the wires coupled up to a permanent cable attached to the lower deck, and which was led down to the mouthing. The sinkers then left the scaffold and connected the permanent cable at the bottom to a large magnet machine, which was always kept locked. The shots were then fired all together, four shots being the maximum that were fired at once. After the prescribed interval the sinkers went up again, and, exercising due caution, entered the box and climbed up on to the scaffold, removing, with the long pole mentioned above, any dangerous pieces and making their roof secure. The scaffold was then cleared by fill- ing the box. When the box was sufficiently full, the man on the lower deck signalled down to the bottom for anyone to stand clear, and, having received a signal that all was safe below and above, he would then open the triggers, release the brake, and let the debris fall to the bottom. The doors were at once shut and locked, and the process repeated till the scaffold was clear. The sides were then trimmed and everything made ready to move up. The capstan rope was then rung for and the chains connected up. The prids on the lower deck were knocked in, and the scaffold lifted until the bottom deck was level with the top of the brickwork, when the prids were knocked out and the scaffold lowered on to them. Next, the shaft was bricked between the decks until the top scaffold was supported by the brickwork and made to share the weight with the prids. The cycle was then repeated. A bell was connected from the level in the Cannel mine to the pit bottom, but generally when the sinkers wished to have the capstan rope raised or lowered they would shout to the hookers-on at the pit bottom through the borehole, which acted like a megaphone. The last few yards below the sump were left in as a protection while sinking through the ground below the Cannel mouthing in the ordinary way, using the scaffold as a headgear ; and this intermediate strata also served as a water dam, the water winding being continued until they broke through, which they did from the top. The contract price for the top portion was £10 a yard for the finished pit 16 ft. diameter, including 14 in. brick- work, and £11 a yard for the lower section, which included bell-mouthing the pit to 20 ft. for the new pit bottom. It will be seen from these figures that the driving of the shaft by this rise method was practically as safe and as cheap as sinking in the usual method. This, the writer thinks, is ample proof as to the success of this method of sinking under these circumstances. The total cost of the extension, including 20 yards of arching at the bottom and putting wooden rods and bearers in the new portion of the shaft, worked out approximately to £25 a yard for labour and materials. This is not really a high figure, and it should be remembered that the winding of both coal and water was not interfered with in any way, either at the pit or in the tunnel, until the last moment. During the sinking only one accident occurred, and that was not serious nor of a nature unusual in ordinary tunnelling, and was in no way due to the sinking scaffold. , The writer is of the opinion that if the same work had to be done again by his company, the same method would be adopted, with the exception that the frame of the scaffold would probably be of steel. Safety Air Doors for Coalmines. Mr. James Ashworth, of Vancouver, contributed the following paper:—Whilst examining No. 5 Mine of the North-western Improvement Company’s coalmine at Ronald, in the State of Washington, U.S.A., the writer came across a simple and ingenious arrangement whereby the opening of the main separation doors between the intake and return air, and the surface and the fan, were so controlled that both doors could not be open or opened at the same time. It seems opportune to send a model of this arrange- ment with a few descriptive notes, to follow Mr. William Clifford’s paper on “ Some Experiences in Reversing the Main Air-Currents in Coalmines.” Under ordinary circumstances, if the air in a mine is reversed, a most serious and dangerous condition is at once established, because the air will be sure to short- circuit at the first doors between the intake and return airways. The Ramsey patent is a cure for this, although it is self-evident that a small leakage would still occur. The whole subject of air-reversal is such that the course to pursue cannot be settled by any written or printed instructions; but one thing is certain, and that is, that to reverse the air-current is a most dangerous operation, and may result in a greater disaster than the original disaster. The writer has only seen one instance of this, and that was the second explosion at the Burley Colliery, in North Staffordshire. He was at the time on his way to visit the mine after the first explosion, which resulted from a shot which killed every living thing in the mine, excepting one horse. Exploring parties had been down the mine and recovered most of the bodies, but then, for some reason which the writer does not now recollect, they were withdrawn, and it was decided to fill up the upcast shaft until a certain mouthing, through which some of the return air entered this furnace shaft, was covered. Throwing dirt down the shaft reversed the air, and after this had proceeded for some time a line was lowered down and measured by an engineer, who reported that the mouthing was covered. A party of engineers was'then organised to go down the downcast shaft to make further explorations. This party were actually on their way to the top of the shaft, when the mine exploded the second time, with very great force, throwing great volumes of smoke and dust out of the downcast shaft only, killing the one horse and smothering a large number of horses in another mine which had not been affected by the first explosion. In explanation of the second disaster it was thought that a blower of gas .or some material had been burning in the upcast shaft, and that the firedamp which had accumulated during the reversal of the air had been carried to this flame and thereby ignited. This is just one of those instances of what might happen in consequence of the reversal of