THE COLLIERY GUARDIAN AND JOURNAL OF THE COAL AND IRON TRADES. Vol. CVII. FRIDAY APRIL 3, 1914. No. 2779. Cement Grout in Water-Bearing Fissures. (From the “Transactions” of the American Institute of Mining Engineers.) By FRANCIS The direct injection of cement grout into water- bearing fissures as a means of checking or stopping the flow of water into shafts and tunnels has been experimented with for a decade or longer, and seems to have been first attempted in Europe. It is only lately, however, that the process has been entirely successful. This success has been accomplished on the Catskill aqueduct, now under construction by the city of New York. This aqueduct in- cludes a number of deep-pressure tunnels, reached by shafts for both waterway and construction purposes. In portions of these shafts and tunnels considerable underground water was met. The contract for the first of these deep-pressure tunnels was let to the T. A. Gillespie Company. This section is known as the Rondout siphon. It leads under the Rondout Valley at a depth of from 400 to 800 feet, and is about 5 miles long. The engineers expected that considerable water would be encoun- tered, but fortunately this was not the case except at one shaft, known as No. 4, which penetrated the rock at a junction between limestone and conglomerate. Water- bearing fissures were encountered almost immediately. At a depth of about 200 ft. a flow of 1,500 gallons per minute was struck. The shaft then contained as many pumps as could be used, and it seemed impossible to sink it further. After vain efforts had been made to proceed, John P. Hogan, a division engineer of the Board of Water Supply, suggested that cementation of the fissures be tried. The process was attempted for the first time in America. Since the shaft was partly full of water it was necessary to drill grout holes with a diamond drill. Platforms were placed on the timbers at the water level, the diamond drill was installed, and six 90 ft. holes were drilled in the bottom of the shaft. Several carloads of cement were pumped through these holes into the fissures, the drill casings being used for grout pipes. This largely cut off the flow of water from the bottom, and sinking could then proceed. After that, water-bearing seams were grouted as soon as encountered, and the contractor was able to finish the shafts and tunnel within the contract time. No. 4 was a rectangular, timbered shaft, with no concrete lining; consequently it was im- possible to cut off any of the water coming in from above the point where grouting was first attempted. On this account large volumes of water had to be pumped until the tunnel was finally sealed. At the next wet shaft the writer had to do with, advantage was taken of the experience gained at shaft No. 4. At this second shaft—No. 4 of the New York City siphon— good progress was made until a depth of about 100 ft. was reached. The first hole drilled in the bottom below this depth struck a stream of water. The flow amounted to about 150 gallons per minute. This was plugged. It was found that each of the 12 holes in the sump cut encountered the same stream of water. As soon as each hole cut the water-bearing seam it was plugged with a tapered wooden plug. After all the holes in the sump had been drilled and plugged in this way, the grout connections were made one at a DONALDSON. time, so as to restrict the flow of water into the shaft. Each connection was made with a piece of 2 in. or 2'5 in. iron pipe about 3 ft. long, threaded at one end and given a long taper at the other. The tapered portion was made rough on the outside by nicking it with a chisel. A heavy iron stop-cock was screwed to the pipe, the tapered end wrapped in several thicknesses of burlap, the wooden plug removed from the drill hole Photo by Beresford. THE EARL OF CRAWFORD AND BALCARRES, who was last week elected president of the Mining Association of Great Britain, is a member of an ancient family that has been closely associated with the coalmining industry of Lancashire for many years. Like his father, the 26th Earl, his lordship, who was born in 1871, is a man of high attainments, and is a recognised authority on art and architecture. He is a trustee of the National Portrait Gallery, hon. secretary of the Society for the Protection of Ancient Buildings, and vice-chairman of the National Trust. As Lord Balcarres, he sat for several years in the House of Commons as Conservative member for the Chorley Division of Lancashire, and was a Junior Lord of the Treasury from 1903 to 1905. Last year he succeeded to the earldom on the death of his father. One of the largest royalty owne'S in the Wigan district, his lordship is chairman of the Wigan Coal and Iron Company Limited, and resides at Haigh Hall, Wigan. It is safe to say that his personality will add still further distinction to the important office which he has now been called upon to fill. and the tapered pipe driven in, the stop-cock being left open. This was the most exciting and the wettest part of the job. After the pipe had been driven in hard the stop-cock was closed. In this case connections were placed in all the wet holes before grouting. The grouting machine or tank used on the aqueduct was the Caniff machine, in which the grout is mixed by air. It is built like an air lock with a door on the top through which cement, sand and water are introduced, and has a 2 in. discharge opening in the bottom and air connections top and bottom. The discharge opening is connected to the grout hole by a heavy rubber hose. Another 2 in. stop-cock is placed at the outlet of the tank and a 2 in. by 1 in. T is placed between the hose and the cock attached to the pipe in the drill hole. Into the side opening of this T a 1 in. stop-cock is screwed. The machine is installed at the bottom of the shaft, and is connected to one of the holes and also to the high-pressure air supply. The 2 in. stop-cock on the machine is closed and the other is opened. The door in the top is opened, a sack of cement, three or four buckets of water, and (if the cavity to be filled is large) a sack of fine sand are poured in, the air connection at the bottom is opened and the air allowed to bubble through and mix the grout. Then very quickly the door is closed, the lower air connection is closed, and the discharge connection and the upper air connection are opened, and the air enters and drives the grout into the cavity. A man stationed at the 1 in. stop-cock keeps opening it a crack ; when air shows instead of grout he closes the 2 in. stop-cock and the machine is recharged. If the cavity is open the charge is pushed in in three or four seconds. By working continuously more than 1,000 batches can be placed in 24 hours. The grouting of the fissure was successful and sinking was resumed. About 50 ft. further down another water-bearing fissure was drilled into, and this, instead of being open, was filled with sand formed by the crushing of metamorphic gneiss due to folding. This sand was carried up out of the drilled holes in large quantities by the water. Grout will not permeate sand, and it was necessary to continue drilling holes and pumping in grout, increasing the pressure at the end from 100 lb. to 400 lb. and 500 lb. to the square inch. The sand was tamped so full of cement that when cut through it was compacted like sand- stone, and contained balls of grout from the size of a fist to as large as a man’s head. The most difficult grouting on the aqueduct was done on the Hudson Siphon, which is a deep siphon tunnel under the Hudson River, at a depth of 1,000 ft. below tide-water. The shafts were sunk by the city forces, after which the contract for the driving and lining of the tunnel and lining the shafts was let. About 150 ft. from the foot of the east shaft the heading cut a water-bearing fissure which flowed about 300 gallons per minute. The full flow did not develop until the cut was blasted. The problem then was to grout this flow against a hydrostatic pressure of 500 lb. per square inch, with no solid rock to which to make grout-pipe connections. This problem was finally solved by the construction of a concrete bulkhead 8 ft. thick across the full section of the head. The concrete was mixed in proportion of 1:2:4, and was heavily reinforced with rails set into holes drilled laterally into the sides, roof and floor of the tunnel. Grout pipes leading into the fissure were set through the bulkhead. After the concrete had set for a week, grout was forced into the fissure—first by the pneumatic process with a high- pressure air compressor, and finally by means of a high- pressure plunger pump, which forced water instead of air into the grout tank. Pressures were reached in this way up to 1,0001b. per square inch. In driving or sinking through rock containing a large number of seams carrying small quantities of water it is not practicable to stop and grout each seam as described above. In this case it is advisable to increase the section